How do projects differ from ongoing work operations?
Projects are temporary and unique.
Which term describes the appointment of a specific resource to a specific task?
Assignment
What is the term for the goals and tasks of a project, and the work required to complete them?
Scope
What is a project milestone?
A major event during the course of a project
What is a project?
A sequence of tasks that must be accomplished within a defined time frame to achieve a desired result
What is project management?
The process of managing multiple interdependent projects to improve the performance of an organization
Which of the following is a document that lists the planned dates for performing tasks and meeting goals defined in a project plan?
Project schedule
How can scope creep undermine the success of a project?
Incremental changes in scope will affect the schedule, cost or performance required to complete the project.
You should schedule meetings with project stakeholders and management during the executing and controlling phases of a project to:
inform them of progress and to handle issues they raise that may affect project scope.
A SWOT analysis is:
a strategic planning method that can be used to evaluate the strengths, weaknesses, opportunities and threats in relation to an organization.
During which project management phase should product testing and performance evaluations occur?
The closing phase
During which project management phase should you conduct a needs analysis; determine project objectives, assumptions and constraints; and develop a Statement Of Work (SOW)?
The initiating phase
What must you know before you can create an effective project schedule?
The tasks necessary to achieve project objectives, the approximate length of time each task will take, the order in which tasks should be performed and the empl
In order to manage scope creep, you can use scheduled meetings to:
review and discuss proposed changes to the project scope.
During which project management phase should you troubleshoot problems and take corrective measures to ensure that all objectives are being met?
The controlling phase